Our bathroom remodeling process

Measurements, material selections, construction and the final walkthrough, in order.

5.0 on Google, 84 reviewsand 5.0 on Yelp, 18 reviews

OfferFree Shower Upgrade Package Through Dec 31, 2026 · Valid with financing. Offer details (opens in a new tab)

From conversation to completion

  1. 01

    Talk it through

    Tell us about the room, what is not working, and what you want to change.

  2. 02

    Plan the room

    Review the layout, materials, scope, and project budget before work starts.

  3. 03

    Protect & prepare

    Plan access, protect the surrounding space, and prepare for demolition.

  4. 04

    Build & finish

    Work through the plumbing, waterproofing, tile, fixtures, and final details.

  5. 05

    Walk it together

    Review the finished room, care instructions, and the remaining punch list.

On site

Your shower, layer by layer

An old fiberglass stall replaced with a tiled shower, shown from the same spot at each stage. The days follow a typical 9-working-day schedule; you get your own with the written scope.

  1. An old fiberglass shower stall with a framed sliding glass door in the corner of a bathroom.
    Step 01 / 05The old shower

    01The old showerBefore work starts

    Your existing fiberglass stall and framed door. At the visit we check the walls, the valve and the floor around it, and measure for the new shower.

  2. The same shower corner opened to the studs, with a new shower valve, water lines, blocking and the drain on the subfloor, and protection on the bathroom floor.
    Step 02 / 05Down to the studs

    02Down to the studsDays 1 to 3

    Floors and the path are protected, and dust barriers go up. The stall, door and drywall come out. We check the framing and subfloor, set the new valve and drain, and add blocking for the glass and grab bars. If we find water damage, we photograph it and price the repair before doing it.

  3. Orange waterproofing membrane over the shower walls, niche, sloped shower pan and curb.
    Step 03 / 05Waterproofing and shower pan

    03Waterproofing and shower panDay 4

    A sloped pan goes down to the drain, then backer board and a continuous membrane cover the walls, niche and curb. A flood test checks it, and you get photos of every layer before tile.

  4. Light gray porcelain wall tile, a tiled niche and a mosaic shower floor.
    Step 04 / 05Tile

    04TileDays 5 to 7

    Wall tile, the niche and the mosaic floor go in, then grout and sealing.

  5. The finished shower with a rain shower head, a handheld shower, black valve trim and a frameless glass door.
    Step 05 / 05The finished shower

    05The finished showerDays 8 and 9

    The shower head, handheld and valve trim go in, then caulk and the walkthrough. Glass is measured after tile and installed 1 to 3 weeks later; a curtain works in the meantime.

Stages of a shower remodel.

Request an on-site consultation

Tell us about your room, and we'll call to set up a free on-site consultation.

Get a free estimateCall (425) 550-9475

Mon to Sat, 9 am to 8 pm. We usually reply within an hour.

Shower tile and niche detail

Before the finish

Work through the details early

Discuss layout, drainage, waterproofing, lighting, and ventilation alongside the materials. Make sure the written scope explains what is included and how changes are handled.

Talk about your project

Timelines

How long a bathroom remodel takes

Every project is different. These are typical times on site when nothing unexpected turns up behind the walls. Your own schedule comes with the written scope.

ProjectOn site
Tub-to-shower conversion or tub replacement, with no serious water damage and no plumbing to move or repair7 to 9 working days
Powder room or half bath3 to 8 working days
Full bathroom remodel, same layout2 to 4 weeks
Large primary bathroom1 to 3 months
Additions, conversions and projects that need restoration1 to 6 months, including design and permits

Before work starts

The visit and measurements take about an hour, the written scope 2 to 3 days, and choosing and ordering materials 1 to 3 weeks. When the work needs a permit, review takes days to weeks, and longer for additions that need drawings.

What makes a project take longer

  • Water damage, rot or mold found after demolition. We photograph it and price the repair before doing it.
  • Moving the drain, the valve or a wall.
  • Permit review and inspection dates set by the city or county.
  • Special-order tile, fixtures and custom glass. Glass is measured after tile and takes 1 to 3 weeks; you can use the shower with a curtain in the meantime.
  • Changes to the plan after work starts.

Step by step

What happens, and when

Every ADD BATH project follows the same visible sequence, so you always know what is happening, who will be in your home and what decision is needed next. Typical timings below are for a full bathroom remodel with the same layout, about 2 to 4 weeks on site; other projects are in the table above. You get your own schedule with the written scope.

  1. Call, text or send photosDay 0

    Tell us what is not working and share a few photos with your ZIP code. Most people get an honest planning range the same or next business day.

  2. In-home visit and measurements1 hour

    We look at the room, the plumbing, the subfloor and the ventilation, measure everything and talk through options and budget. No three-hour sales pitch.

  3. Written scope and quote2 to 3 days

    You receive a line-by-line scope with allowances, unit prices for hidden damage, the schedule and the payment milestones. The quote stays valid for 30 days.

  4. Selections and ordering1 to 3 weeks

    Choose tile, vanity, fixtures and glass style with our guidance. Special-order items can take longer, so we confirm lead times before scheduling demolition.

  5. PermitsDays to weeks

    When the scope needs a permit, we apply for it. Some cities, such as Lynnwood, require plan review for interior remodels.

  6. Protection and demolition1 to 2 days

    Floors and the path through your home are protected and dust barriers go up. Old materials come out and are hauled away.

  7. Repairs, rough plumbing and electrical2 to 5 days

    We repair any damaged framing or subfloor (with your approval), add blocking, and licensed trades complete rough plumbing and wiring. Inspections follow.

  8. Waterproofing and flood test2 to 4 days

    Backer board and a continuous membrane go on walls and floor, then a 24-hour flood test. You get photos of every layer before tile.

  9. Tile and grout4 to 8 days

    Wall and floor tile, niches and bench, then grout and sealing.

  10. Fixtures, vanity and finishes2 to 4 days

    Vanity, top, toilet, trim, fan, lighting, accessories and paint. Final inspections when required.

  11. Glass and final walkthrough1 to 3 weeks after tile

    Glass is measured after tile and installed when ready. We walk the room together, finish any punch-list items and review care and warranty.

How to prepare your home

  • Plan to use another bathroom while yours is out of service
  • Clear the bathroom and the path to it, including medicine cabinets
  • Make space for parking and a materials drop-off
  • Keep pets secured on work days; inspectors also require this
  • Know where your main water shutoff and electrical panel are
  • Expect water-off windows; we tell you about them in advance

Communication during the project

Project management

Our team coordinates the construction schedule and trade work. We review questions and proposed changes with you as the remodel progresses.

Changes in writing

Any change to the scope or price is written and approved by you before the work is done.

Photo record

You receive photos of the waterproofing, plumbing and repairs that end up behind the tile.

Free Shower Upgrade Package through Dec 31, 2026 (opens in a new tab)

Free consultation

Schedule a visit

Pick a day and a time window for a free on-site consultation. We'll call to confirm.

What's included

  • Measurements and a look at your bathroom, at your home
  • 3D design of your new layout
  • Material selections that work together
  • A written scope and quote
  • Financing options through Wisetack
  • 2-year workmanship warranty

Prefer to talk? Call (425) 550-9475

Step 1 of 30% complete
Pick a day and time

Choose a time window for your free consultation. This is a request, not a booked appointment. We'll call to confirm.

Select a time window above.

Pacific Time. Morning 9 to 12, afternoon 12 to 4, evening 4 to 8.

Planning guides

More on planning a bathroom

Focus on your project choices. Close this view to return to the page without losing your answers.

ADD BATHGet an estimateYour bathroom, your choices.

Choose your service and preferred consultation date. Close this view to return without losing your answers.

ADD BATHRequest a visitLet's make room for your project.